Main

News

Media Releases

Videos

Photo Gallery


Repair Works In Progress


LTA Sets Up Independent Investigation Panel

Repair works at Nicoll Highway is in progress, as LTA fills up the cracks around the incident site with concrete to stabilise the ground. We have also set up an independent panel to investigate into the cause of the collapse of the Nicoll Highway work site.

Investigation Panel On the Collapse of Nicoll Highway Work Site

The panel is chaired by Professor Yong Kwet Yew, Professor of Civil Engineering and Vice President of the National University of Singapore, and comprises Professor Wong Kai Sin, Associate Professor, School of Civil & Structural Engineering, Nanyang Technological University and Mr Teh Hee Seang, Managing Director of T.Y. Lin South East Asia Pte Ltd. They are geo-technical and structural experts.

The panel has been tasked to review the design and construction of the works at Nicoll Highway as well as other works on the Circle Line. The panel will establish the cause of failure of the temporary works, suggest recovery measures to restore the construction works and make recommendations to improve the safety of design and construction for future works.

Background on Incident and Measures Taken So Far

At about 3.30pm on 20 April 2004, the temporary wall supporting the excavation site for the tunnels leading towards the Nicoll Highway MRT station along Circle Line Stage 1 collapsed, resulting in major soil subsidence and the caving in of Nicoll Highway. At the time of the incident, the contractor, Nishimatsu Construction Co. Ltd/Lum Chang Building Contractors Pte Ltd Joint Venture was carrying excavation works for the construction of tunnels.

Soil subsidence affected an area measuring 100 metre by 150 metre. It also disrupted the utility supplies in the area but these were restored by the various utilities agencies shortly.

The Singapore Civil Defence Force (SCDF) was mobilised immediately to start rescue operations. LTA engineers and management team was also on site to manage the situation.

LTA has been working closely with SCDF to stabilise the incident site to support the rescue operations in a safe manner. We have also diverted the traffic and public bus services.

In addition, we have been monitoring the ground movements in the area and put in place the following measures:

  • Mounted survey markers at Golden Mile Complex, Merdeka Bridge and Crawford Underpass
  • Installed slope protection measures along Nicoll Highway from Golden Mile
  • Installed temporary bank using cement bags to stop water flow onto incident site
  • Filling up cracks around the incident site to stabilise the ground and prevent water seepage

Our immediate concern was also with the safety of the surrounding buildings and we are continuing to carry out checks on the buildings with BCA and ensure that they are safe for use.

Works at other LTA work sites are not affected. Nonetheless, our staff is monitoring all activities closely to ensure safety at the sites.

"We are deeply saddened by this unfortunate incident. Our thoughts are with the workers and their families. We are doing all we can to assist SCDF on the rescue measures, and we are rendering the families all the necessary support that they need," said Mr Ho Meng Kit, Chief Executive of the Land Transport Authority.

LTA would like to assure the public that we are doing all that we can to ensure the safety of the surrounding area and return the situation to normal. Given the extent of this incident, we would like to seek public's understanding that repair works may take some time and we apologise for the inconvenience caused.

 
Source: Land Transport Authority, 21 Apr 2004

News Updates >>>
More >>>

back to Channelnewsasia.com >>

Copyright © MCN International Pte Ltd. All Rights Reserved.
Use of this Site is subject to our terms and conditions of use.
Your continued use of this Site shall be construed as your agreement to abide by our terms and conditions of use.