First Stage Of Repair Works For Nicoll Highway Completed

The Land Transport Authority (LTA) and its contractors have completed the first stage of repair works at the Nicoll Highway incident site. This involved pumping foam concrete to fill up the deep cavities on site as well as the surrounding area.

"Close to 2,900 cubic metres of concrete was used, raising the level at the collapsed site to about 15 metres below ground level," said Guy Taylor, Senior Project Manager for Stage 1 of the Circle Line.

The next stage of repair works has begun this morning. Mixed concrete, comprising of soil and cement are poured into the site to form a level platform. This mixture of concrete holds the ground in place, further stabilising the ground conditions on site. This stage of repair works is expected to complete by first week of May 2004. Thereafter, the removal of steel and concrete debris will take place.

Separation of Merdeka Bridge

"More than 90% of the works to cut the bridge have been carried out. We expect the separation of the Merdeka Bridge to be completed by tonight, subject to the weather conditions," said Quek Song Kim, Manager for Road Structure and Facilities Management.

LTA and its contractors have finished coring works on the carriageway leading towards the National Stadium. Works on the carriageway leading to the city will be completed by tonight.

 
Source: Land Transport Authority, 27 Apr 2004

News Updates >>>
More >>>

back to Channelnewsasia.com >>

Copyright © MCN International Pte Ltd. All Rights Reserved.
Use of this Site is subject to our terms and conditions of use.
Your continued use of this Site shall be construed as your agreement to abide by our terms and conditions of use.